πŸ” Clash Detection Tracker
5 Total
2 Open
2 In Progress
1 Resolved
2 Critical
Total Clashes
5
Open
2
In Progress
2
Resolved
1
Rejected
0
Critical
2
Filter:
IDDisciplinesDescriptionLocation PriorityStatusAssignedDue DateActions
CLH-001 HVACvsStructure Large supply air duct penetrates primary beam at grid B-4 without sleeve Level 3, Grid B-4 πŸ”΄ Critical Open M. Torres Jun 25 ⚠
CLH-002 PlumbingvsElectrical Domestic hot water riser conflicts with main electrical cable tray in ceiling void Level 2, Riser Core A 🟑 Major In Progress S. Kim Jun 28
CLH-003 ArchitecturevsStructure Raised floor in server room overlaps structural column base plate Level 1, Room 104 🟑 Major Resolved A. Patel Jun 15
CLH-004 Fire ProtectionvsHVAC Sprinkler branch line crosses HVAC supply duct with only 20mm gap Level 4, Zone C πŸ”΄ Critical In Progress J. Reyes Jun 22
CLH-005 ElectricalvsStructure Conduit bundle routing conflicts with shear wall opening on north facade Level 5, North 🟒 Minor Open Unassigned Jul 5