Space Shuttle Challenger, 1986: A Joint Seal and a Launch Decision
The Presidential Commission found that the loss of Challenger was caused by the failure of the seals in a joint of the right Solid Rocket Motor, and that the launch decision process had a serious flaw.
Aerospace & Space · Last reviewed
What happened
The Space Shuttle Challenger (mission 51-L) was lost shortly after launch on January 28, 1986. The Presidential Commission on the Space Shuttle Challenger Accident, often called the Rogers Commission, reported its findings to the President on June 6, 1986.
What the Commission found
- Physical cause: the Commission concluded that the loss was caused by a failure in the joint between the two lower segments of the right Solid Rocket Motor. The specific failure was the destruction of the seals meant to prevent hot gases from leaking through the joint during the propellant burn. The Commission found that no other element of the Shuttle system contributed.
- The Commission examined the other possibilities in detail, including the External Tank, the Space Shuttle Main Engines and the payload, and ruled each of them out.
- Decision making: Chapter V of the report states that the decision to launch was flawed. Those who made it were unaware of the recent history of problems with the joint seals, of the contractor's initial written recommendation against launching at temperatures below 53 degrees Fahrenheit, and of the continuing opposition of the contractor's engineers after its management reversed its position. The Commission found failures in communication that led to a decision based on incomplete and sometimes misleading information, and concluded that if the decision-makers had known all the facts, it is highly unlikely they would have decided to launch on January 28, 1986.
- The ambient temperature before launch was the coldest of any launch up to that time.
Apply the lesson
- Think of a design limit your team relies on that was set from past successful use and not from testing at the extremes. What conditions are outside the experience behind it?
- When an engineer says "I do not think this is safe", where in your process does that statement go, and who must answer it in writing?
- Write the decision rule for a go/no-go call so that the burden of proof is on showing the system is safe, not on proving it is unsafe.
Engineering lesson: a concern raised by the people closest to the hardware has to reach the decision-maker in clear terms, and the default when the data are uncertain must be the safe one.
What the Commission recommended
The Commission adopted recommendations to help assure the return to safe flight. The first concerned the design:
- The faulty Solid Rocket Motor joint and seal must be changed, either by a new design that eliminates the joint or by a redesign of the current one. No design option should be precluded because of schedule, cost or reliance on existing hardware.
- The joints should be fully understood, tested and verified, and the integrity of the joints should be insensitive to dimensional tolerances, handling, assembly, inspection, environment and operating pressure.
- Certification should include tests that duplicate the actual launch configuration as closely as possible, over the full range of operating conditions including temperature.
- NASA should ask the National Research Council to form an independent oversight committee to oversee the design effort.
Other recommendations dealt with how the program was run. The Commission found that project managers for the Shuttle elements felt more accountable to their center management than to the Shuttle program organization, and it recommended giving the Program Manager clear authority for all STS operations. It also recommended a Shuttle Safety Advisory Panel reporting to the Program Manager.
Related tools and labs
Calculators, labs and simulators are part of the All-Access Pass.
More case studies
- Mars Climate Orbiter: When Units Become an Interface Failure
- Space Shuttle Columbia, 2003: A Foam Strike and Organizational Causes
- Alaska Airlines Flight 1282, 2024: A Door Plug and a Parts-Removal Process
- Tacoma Narrows Bridge, 1940: Wind and a Slender Deck
- Hyatt Regency Kansas City Walkways, 1981: A Connection Detail Changed During Construction
- BP Texas City Refinery, 2005: A Tower Overfilled and Trailers in the Wrong Place
- Imperial Sugar Refinery, 2008: A Dust Explosion Fueled by Accumulations
Questions
Did engineers raise concerns before the launch?
The Commission report records that the contractor's engineers opposed the launch and that its initial written recommendation advised against launching below 53 degrees Fahrenheit. The finding is that this information did not reach the people who made the decision in a form that would have changed it.
Where can I read the report?
The full report is hosted by NASA History at history.nasa.gov, linked below. Chapter IV covers the cause of the accident and Chapter V covers the decision to launch.
What did the Commission recommend first?
That the faulty Solid Rocket Motor joint and seal be changed, with no design option ruled out for reasons of schedule, cost or existing hardware, and with independent oversight of the redesign.
Did the Commission look at program management?
Yes. It found that project managers felt more accountable to their own center than to the Shuttle program organization, and recommended redefining the Program Manager's authority and creating an independent safety panel.
Sources
Educational material. Examples use simplified, hypothetical inputs and are not a design, a construction document or professional engineering advice. Confirm requirements with the codes and standards adopted where the work is built and with a licensed engineer.