โ† Civil Site Development Studio
๐Ÿ—๏ธ

Earthwork Cut/Fill Balance Simulator

Adjust the proposed grade plane across the grid to balance cut & fill and minimize import/export

โš 
Net EXPORT: 666 CY
666 CY of excess cut material must be hauled off site.

๐Ÿ“ Proposed Grade Plane

Proposed base elevation100 ft
Grade in X direction0 %
Grade in Y direction0 %

โš™๏ธ Grid & Material

Grid spacing50 ft/cell
Shrink/swell factor15 %
Shrink/swell is applied to the fill volume to account for compaction.

๐Ÿ“Š Results

Total Cut2551 CY
Total Fill1639 CY
Fill w/ shrink/swell1885 CY
Net Import/Export+666 CY
Cell area2,500 ftยฒ
Grid5ร—5 cells
Average-end / grid method: Cut/fill volume is estimated per cell as the average corner depth ร— cell area. A balanced site (net โ‰ˆ 0 CY) avoids costly off-site haul or borrow. Adjust the proposed plane to tilt with the existing terrain.
Cut / Fill Map ยท Cell depth in feet (existing โˆ’ proposed)
2.91.80.4-0.6-0.54.33.31.90.91.03.82.81.30.40.41.70.6-0.8-1.8-1.7-0.4-1.5-2.9-3.9-3.8Columns (X) โ†’Rows (Y) โ†’
Cut (excess)
Fill (needed)
Balanced (~0)