← Electrical Systems Studio
🔌

Renewable Interconnection Screening

FERC SGIP Fast-Track Screens · IEEE 1547-2018

When to use: Screening-level check of whether a proposed solar, wind, or BESS project at a point of interconnection (POI) is likely to qualify for a fast-track / simplified utility interconnection review versus a full impact study. Mirrors the screening logic used in FERC's Small Generator Interconnection Procedures (SGIP) and many state fast-track tariffs. Educational approximation only — always confirm against the interconnecting utility's actual tariff and a qualified engineer.

Project & Circuit Parameters
solar/wind/BESS
kW
kW
reverse power-flow screen
kW
Key Screening Rules
Screen 1: capacity ÷ circuit peak load ≤ ~15%
Screen 2: capacity ≤ 100 kW on shared xfmr, ≤ 20% of min. daytime load
Screen 3: inverter-based + IEEE 1547-2018 ride-through/anti-islanding
Screen 4: ≥69 kV transmission POI — outside small-gen fast-track scope
Screening Result
Likely requires supplemental review
3 of 4 screens passed
Results
Generator Capacity500.0 kW
Feeder Peak Load8000.0 kW
% of Circuit Peak Load6.3%
Feeder Min. Daytime Load2000.0 kW
% of Min. Daytime Load25.0%
✓ PASS
Peak Load Screen
✗ FLAG
Voltage/Reverse-Flow Screen
✓ PASS
Ride-Through Screen
✓ PASS
Voltage Class Screen
Why Escalation Was Flagged
Capacity exceeds 100 kW AND is 25.0% of feeder minimum daytime load — flag for reverse power flow / voltage rise review.
References
FERC Order 2222 / Small Generator Interconnection Procedures (SGIP)
IEEE 1547-2018 — ride-through & anti-islanding
State fast-track / simplified interconnection tariffs
Utility-specific interconnection handbook (varies by jurisdiction)
Educational screening approximation of common FERC SGIP / state fast-track interconnection criteria. Actual interconnection requirements are utility- and jurisdiction-specific — always consult the local utility's interconnection tariff/procedures and a qualified engineer before relying on this result.

About the Renewable Interconnection Screening Tool

This tool applies screening-level logic modeled on FERC's Small Generator Interconnection Procedures (SGIP) fast-track screens to estimate whether a proposed solar, wind, or battery storage project is likely to qualify for a simplified/fast-track utility interconnection review or will likely require a full interconnection impact study. It flags the specific criteria driving any escalation so the reasoning is transparent.

How fast-track screening works

FERC's SGIP framework (and the many state-adopted fast-track/simplified tariffs modeled on it) uses a series of pass/fail technical screens applied at the proposed point of interconnection (POI) before deciding whether a project needs a full interconnection study. Two of the most common screens compare the proposed generator's nameplate capacity to the host circuit's load characteristics: (1) aggregate generation on the line section as a percentage of the circuit's annual peak load — commonly a ~15% threshold — and (2) a reverse power-flow / voltage-rise screen, often triggered when capacity exceeds 100 kW on a shared secondary/service transformer or 20% of the feeder section's minimum daytime load. Falling within these thresholds suggests the circuit can absorb the new generation without a detailed load-flow and protection study.

Why ride-through and anti-islanding matter

IEEE 1547-2018 is the governing technical standard for interconnecting distributed energy resources (DER) to the grid, and it defines mandatory voltage/frequency ride-through behavior and anti-islanding protection for inverter-based resources. Many fast-track programs treat IEEE 1547-2018 compliance — with correctly configured ride-through and anti-islanding functions — as a precondition for simplified review, because a compliant inverter is expected to ride through minor grid disturbances rather than nuisance-tripping or, worse, continuing to energize an unintentional island after the utility source disconnects. A non-inverter-based (rotating) generator, or an inverter that is not confirmed 1547-2018 compliant, cannot rely on these built-in protective functions, so utilities typically require a full technical review of protection coordination and anti-islanding scheme regardless of project size.

Why reverse power flow and voltage class matter

Distribution feeders are engineered assuming one-directional power flow from the substation to the load. A generator large enough relative to the local minimum daytime load can reverse that flow, causing voltage rise beyond regulator/LTC design assumptions, mis-operation of protective devices calibrated for one-way fault current, and possible islanding hazards for line crews. That's why the minimum daytime load (not just peak load) is screened separately — a project can pass the peak-load screen yet still create daytime reverse flow when the circuit is lightly loaded. Transmission-voltage interconnections (≥69 kV) are excluded from small-generator fast-track processes entirely, since they involve bulk power system reliability studies (NERC/regional transmission organization review) rather than local distribution engineering.

Frequently asked questions

Is this tool a substitute for my utility's actual interconnection application?

No. This is an educational screening approximation of the general logic used across many FERC SGIP-based and state fast-track tariffs. Every utility publishes its own interconnection tariff/handbook with specific thresholds, application forms, and study fees that can differ from the generic values used here. Always start with the actual interconnecting utility's procedures.

What does "fast-track eligible" actually mean in practice?

Fast-track (or "simplified"/"expedited") review means the utility can typically approve interconnection based on a shorter technical screening process rather than a full System Impact Study and Facilities Study, saving significant time and study cost. Passing initial fast-track screens does not guarantee approval — a supplemental review can still be triggered if any individual screen fails, and the utility retains discretion to require additional study.

Why does a battery storage (BESS) project use the same screens as solar or wind?

FERC SGIP screens are based on the interconnecting facility's nameplate export capability at the POI, not its energy source. A BESS that can export power to the grid is screened the same way as a solar or wind generator of equivalent capacity, since the technical concerns (reverse power flow, voltage rise, protection coordination, ride-through) are driven by the point of interconnection behavior, not the underlying generation technology.

My project fails one screen — does that mean it can never interconnect?

No. Failing a fast-track screen only means the project is routed to a more detailed study process (supplemental review or full System Impact Study) rather than automatic disqualification. Many projects that fail initial screens are ultimately approved for interconnection, sometimes with additional equipment (e.g., voltage regulation, upgraded protection, or feeder upgrades) identified and funded through the study process.

🎓

Try our Electrical Studio

More calculators, simulators, and guides for this discipline.

Related tools & guides

NEC 705 Interconnection Current LimitMicrogrid Islanding SimulatorRenewable Energy Reference GuideArc Flash Incident Energy