Fire Pump Duty: Flow, Pressure and Elevation
Build a simplified pressure budget for a 750 gpm demand with elevation, friction and suction pressure, and check it against a supplied fire pump curve.
Fire Protection · Last reviewed
Given
A building system needs 750 gpm at 85 psi at the top of the riser. The riser top is 60 ft above the pump. At 750 gpm the friction loss in the piping is 14 psi and the backflow preventer and valves lose 7 psi. The water supply gives 40 psi at the pump suction at 750 gpm. All numbers are exercise values. The supplied pump curve (centrifugal fire pump rated 750 gpm at 100 psi) gives 118 psi at no flow (churn), 100 psi at 750 gpm and 70 psi at 1,125 gpm (150% of rated flow). The maximum static pressure at the suction is 55 psi.
Find
The net pressure the pump must add, whether the pump meets it, and the highest pressure the system sees.
Solution
Related tools and labs
Calculators, labs and simulators are part of the All-Access Pass.
More worked problems
- Sprinkler Flow from K-Factor and Pressure
- Fire Alarm Control Panel Battery Calculation
- Fire Alarm NAC Voltage Drop with Distributed Devices
- Sprinkler Branch Line: Work Back from the Remote Head
- Fire-Water Storage: Demand, Duration and Usable Volume
- Challenge: Can You Add Two Sprinkler Pressures?
- Size the Branch Circuit for a 40 hp, 460 V Motor
- Voltage Drop on a 240 V Single-Phase Feeder
Questions
Why check the maximum pressure?
At no flow the pump produces its churn pressure on top of the suction pressure. The pipes and fittings must withstand that sum.
Is 8 psi a good margin?
The margin here is an exercise result. Real projects follow the applicable standard and the authority having jurisdiction, and typically leave margin for future changes and pump wear.
What would a larger elevation do?
Each extra foot of height adds 0.433 psi. 100 ft instead of 60 ft would add 17.3 psi and the pump would no longer meet the duty.
Educational material. Examples use simplified, hypothetical inputs and are not a design, a construction document or professional engineering advice. Confirm requirements with the codes and standards adopted where the work is built and with a licensed engineer.