Short answer: on-off control is enough when the process is slow, a band of variation is acceptable and the actuator can switch often, such as a room thermostat. PID is the better choice when the process must hold close to a setpoint, the actuator is modulating, or frequent switching would wear the equipment.
| On-off (with hysteresis) | PID | |
|---|---|---|
| Output | Fully on or fully off | Continuous, from 0 to 100% |
| Variation around the setpoint | A band, set by the hysteresis and the process speed. The process always cycles | Can hold very close to the setpoint when tuned |
| Actuator | A relay, contactor or on-off valve. Cycling wears it | A modulating valve, a drive or a proportional output, or a time-proportioned relay |
| Tuning | One setting: the differential (hysteresis) | Three settings (gain, integral time, derivative time) that need tuning |
| Process types | Slow processes with large thermal mass, tolerant of swings | Faster or tighter processes, such as flow, pressure and precise temperature |
| Disturbances | Responds after the band is crossed | Corrects continuously, with integral action removing steady offset |
| Implementation effort | Minimal | More: instrument range, tuning, anti-windup, testing |
| Typical uses | Thermostats, pump start-stop on tank level, compressor pressure switches | Process temperature, flow loops, pressure control, speed control |
Related tools and labs
Calculators, labs and simulators are part of the All-Access Pass.
More comparisons
- PLC vs DCS: Which Control System for the Plant?
- RTD vs Thermocouple: Which Temperature Sensor Fits?
- 4–20 mA vs 0–10 V: Which Analog Signal Should You Use?
- Two-Wire vs Four-Wire Transmitters
- Modbus RTU vs Modbus TCP
- BACnet vs Modbus: Which Protocol Fits Building Automation?
- VFD vs Soft Starter: Which One for an AC Induction Motor?
- Star-Delta vs Direct-on-Line Motor Starting
Questions
Is PI enough?
For many loops, yes. The derivative term is often not needed, and it amplifies measurement noise.
What does hysteresis do?
It sets a gap between the switch-on and switch-off points. A wider gap reduces switching and widens the variation.