Use throughput, bottlenecks and quality evidence to understand a process.
Free · No sign-in required3 lessonsWorked examples & practiceBeginner
0 of 3 lessons checked · Progress is saved in this browser.
01 / SYSTEM VIEWInputs
02 / SYSTEM VIEWProcess stages
03 / SYSTEM VIEWUseful output
This map connects the course ideas; it is not a detailed engineering schematic.
LESSON 1 / 3 · FREE
Process boundaries and throughput
Your goal: Measure completed output over a defined interval.
Understand the idea
A process map follows work through stages, queues and decisions. Throughput counts completed output per time; work in progress counts items still in the system. Define whether output is attempted, completed or accepted before comparing production rates.
Worked example
A fictional line completes 120 accepted units in 2 h: 60 accepted units/h. This is not the rate of one fast machine inside the line.
Try it yourself
A line completes 180 accepted units in 3 h. Find average throughput.
Your goal: Find the limiting stage in an ideal serial process.
Understand the idea
In a simple serial line without rework or downtime, long-run output cannot exceed the slowest stage’s capacity. Buffers and scheduling affect short-term behavior. Improving a nonlimiting stage may increase idle time or inventory without raising system throughput.
Worked example
Supplied stage capacities of 50, 40 and 60 units/h limit ideal serial throughput to 40 units/h. This ignores availability and quality losses.
Try it yourself
Stages can process 70, 45 and 80 units/h. Find ideal bottleneck capacity.
Your goal: Separate accepted output from attempted output.
Understand the idea
Yield is accepted output divided by a specified input or attempted count. State whether the measure is first-pass or after rework. A high final yield can hide substantial rework effort; a meaningful improvement also considers defects, time and resource use.
Worked example
Of 200 attempted parts, 180 pass on their first attempt. First-pass yield is 90 percent; later rework must be reported separately.
Try it yourself
Of 250 attempts, 225 pass first time. Find first-pass yield.
Explain each worked example in your own words, check the units and identify one assumption that could change the result. Then use the linked labs or roadmap to apply the ideas to a broader task.
Practice progress is a study aid, not a professional qualification or proof of field competence.
Continue in Industrial & Systems Engineering
Apply these foundations in an available course, lab or roadmap. The linked resource’s access rules still apply.
These original lessons use simplified models and explicitly supplied practice values. Calculations teach concepts; they do not select real equipment, establish code compliance or authorize field work. Follow the linked references and advanced resources for deeper study.
Updated · Study progress stays in this browser. There is no certificate or paid gate for these lessons.