Size a Three-Phase Transformer for a Mixed Load
Total the connected kVA of lighting, receptacle, HVAC and miscellaneous loads, add growth, choose a standard kVA rating, and find the primary and secondary full-load currents.
Electrical & Power · Last reviewed
Given
A small commercial building on a 480 V primary, 208Y/120 V secondary, 3-phase dry-type transformer. Calculated loads: lighting 18 kVA, receptacles 24 kVA, HVAC 45 kVA, miscellaneous 12 kVA. The owner wants 20% spare capacity for future load.
Find
The standard transformer size and the full-load current on each side.
Solution
Related tools and labs
Calculators, labs and simulators are part of the All-Access Pass.
More worked problems
- Size the Branch Circuit for a 40 hp, 460 V Motor
- Voltage Drop on a 240 V Single-Phase Feeder
- Office Lighting Load: Connected Power and Current
- Challenge: The Current That Looks Too High
- Power Factor Correction: How Many kvar of Capacitors?
- Short-Circuit Current at a Transformer Secondary
- Pump Head, Shaft Power and Motor Size
- Sensible Cooling Capacity from Airflow and Temperature Difference
Questions
Why 150 kVA and not 118.8 kVA?
Transformers are made in standard sizes. You pick the first standard size at or above the calculated load.
Does this size the primary and secondary protection?
No. The overcurrent protection and conductors follow the code rules for transformers, which use these currents as the starting point.
What about the transformer impedance and short-circuit current?
That is a separate calculation. See the short-circuit problem in this section.
Does transformer impedance matter for sizing?
It does not set the kVA size, but it affects the voltage regulation under load and the available fault current. Check both after you choose the size.
What about transformer efficiency rules?
Many jurisdictions regulate the minimum efficiency of distribution transformers. Check the rules that apply to the project when you specify the unit.
Educational material. Examples use simplified, hypothetical inputs and are not a design, a construction document or professional engineering advice. Confirm requirements with the codes and standards adopted where the work is built and with a licensed engineer.